UNDP Project Portal

Climate actions supported by UNDP,
funded by Green Climate Fund and partners

Project Details

Project Title Safeguarding rural communities and their physical assets from climate induced disasters in Timor Leste
Project Size GCF medium (USD 50-≥250 million)
Project Coverage Country
Region Asia & Pacific
Country Timor Leste
Participating Countries Timor Leste
Result Areas Most vulnerable people and communities
Infrastructure and built environment
Ecosystems and ecosystem services
Project Status Funding proposal approved
Project Grant Amount (USD) 22,356,805.00
Project Duration (months) 72 
Project Start Date 09/03/2020
Project End Date 09/03/2026
GCF Focus Adaptation
Safeguarding Rural Communities and their Physical Assets from Climate Induced Disasters in Timor-Leste

UNDP, Timor-Leste launch GCF-backed project to protect rural communities against climate change

Green Climate Fund approves $22.4 million for climate-resilient infrastructure in Timor-Leste

Project Documents
Feasibility Study (Annex)

NDA No-objection Letter (Annex)

Safeguards Framework (Annex)

Map indicating the location of the project/programme (Annex)

Timetable of project/programme implementation/Multi-Year Work Plan (Annex)

Confirmation letter or letter of commitment for co-financing (Annex) (pdf)

Confirmation letter or letter of commitment for co-financing (Annex) (pdf)

Confirmation letter or letter of commitment for co-financing (Annex) (pdf)

Confirmation letter or letter of commitment for co-financing (Annex) (pdf)

Confirmation letter or letter of commitment for co-financing (Annex) (pdf)

GCF Funding Proposal

Environmental and Social Report Disclosure (Annex)

Project Timelines
  • GCF FP Submission (first)

    24/06/2018

  • GCF FP Submission (last)/awaiting GCF review/approval

    01/07/2019

  • GCF feedback/comments received on FP (first)

    08/10/2018

  • GCF feedback/comments received on FP (last)

    11/12/2018

  • Technical Advisory Panel feedback/comments received on FP

    31/05/2019

  • GCF Board Approval

    08/07/2019

  • FAA Effectiveness/Project Start

    09/03/2020

  • Disbursement Request Submission

    22/05/2020

  • Actual Date of First Disbursement (from GCF)

    04/06/2020

  • Inception Workshop

    11/09/2020

  • Interim Independent Evaluation

  • Project Completion